Arizona · federal rates
Mohave County, Arizona: Davis-Bacon wage rates (2026)
5 federal wage determinations cover Mohave County. Rates below were taken from SAM.gov on 2026-09-20.
Residential
AZ20260003, modification 1 (published 2026-05-18)
Common trades from this wage determination. It lists 15 classifications in total; the full text is on SAM.gov.
| Trade | Classification | Base | Fringe | Listed total | Where the rate comes from |
|---|---|---|---|---|---|
| Electrician | ELECTRICIAN/WIREMAN | $12.14 | $1.83 | $13.97 | DOL survey SUAZ2004-006, 2004-03-08 — survey rate from 2004; check whether your contract uses it |
| Plumber / pipefitter | PLUMBER | $15.13 | $1.18 | $16.31 | DOL survey SUAZ2004-006, 2004-03-08 — survey rate from 2004; check whether your contract uses it |
| Carpenter | CARPENTER METAL STUD FRAMING | $15.00 | $0.00 | $15.00 | DOL survey SUAZ2004-006, 2004-03-08 — survey rate from 2004; check whether your contract uses it |
| Laborer | LABORERS: GENERAL/CLEANUP | $8.72 | $0.00 | $8.72 | DOL survey SUAZ2004-006, 2004-03-08 — survey rate from 2004; check whether your contract uses it |
| LABORERS: FORM SETTING | $9.19 | $0.36 | $9.55 | DOL survey SUAZ2004-006, 2004-03-08 — survey rate from 2004; check whether your contract uses it | |
| Power equipment operator | POWER EQUIPMENT OPERATORS: TRACTOR | $17.00 | $0.36 | $17.36 | DOL survey SUAZ2004-006, 2004-03-08 — survey rate from 2004; check whether your contract uses it |
| POWER EQUIPMENT OPERATORS: LOADER | $12.87 | $0.00 | $12.87 | DOL survey SUAZ2004-006, 2004-03-08 — survey rate from 2004; check whether your contract uses it | |
| POWER EQUIPMENT OPERATORS: BLADE/GRADER | $10.00 | $0.00 | $10.00 | DOL survey SUAZ2004-006, 2004-03-08 — survey rate from 2004; check whether your contract uses it | |
| POWER EQUIPMENT OPERATORS: (BACKHOE) | $13.12 | $0.00 | $13.12 | DOL survey SUAZ2004-006, 2004-03-08 — survey rate from 2004; check whether your contract uses it | |
| Cement mason / concrete finisher | CEMENT MASON/FINISHER | $13.82 | $0.36 | $14.18 | DOL survey SUAZ2004-006, 2004-03-08 — survey rate from 2004; check whether your contract uses it |
| Bricklayer / tile / terrazzo | TILE SETTER | $13.33 | $0.00 | $13.33 | DOL survey SUAZ2004-006, 2004-03-08 — survey rate from 2004; check whether your contract uses it |
| Painter | PAINTER | $10.41 | $0.44 | $10.85 | DOL survey SUAZ2004-006, 2004-03-08 — survey rate from 2004; check whether your contract uses it |
| Roofer | ROOFER | $10.29 | $0.00 | $10.29 | DOL survey SUAZ2004-006, 2004-03-08 — survey rate from 2004; check whether your contract uses it |
Heavy
AZ20260006, modification 1 (published 2026-05-18)
Common trades from this wage determination. It lists 33 classifications in total; the full text is on SAM.gov.
| Trade | Classification | Base | Fringe | Listed total | Where the rate comes from |
|---|---|---|---|---|---|
| Electrician | ELECTRICIAN | $16.00 | $2.84 | $18.84 | DOL survey SUAZ1994-012, 1994-02-01 — survey rate from 1994; check whether your contract uses it |
| Plumber / pipefitter | PLUMBER/PIPEFITTER (MARICOPA, MOHAVE, PINAL, AND YUMA) | $54.15 | $19.80 | $73.95 | Union agreement PLUM0469-005, 2025-01-03 · Price a crew using this row |
| Carpenter | PILEDRIVERMAN | $27.38 | $12.44 | $39.82 | Union agreement CARP0408-004, 2018-07-01 · Price a crew using this row |
| CARPENTER (INCLUDING FORM WORK) | $28.08 | $12.74 | $40.82 | Union agreement CARP0408-004, 2018-07-01 · Price a crew using this row | |
| PILEDRIVERMAN | $27.38 | $12.44 | $39.82 | Union agreement CARP0408-004, 2019-07-01 · Price a crew using this row | |
| CARPENTER (INCLUDING FORM WORK) | $28.08 | $12.74 | $40.82 | Union agreement CARP0408-004, 2019-07-01 · Price a crew using this row | |
| MILLWRIGHT ZONE DEFINITIONS FOR MILLWRIGHTS: MILEAGE SHALL BE CALCULATED FROM THE CONSTRUCTION SITE TO THE CITY HALL IN PHOENIX OR TUCSON, OR TO THE WORKMEN'S RESIDENCE, WHICHEVER IS LESS: ZONE 1: 0-30 MILES ZONE 2: 31-49 MILES ZONE 3: 50 MILES AND OVER | $40.61 | $17.53 | $58.14 | Union agreement CARP1914-001, 2019-09-01 · Price a crew using this row | |
| Laborer | LABORERS: GROUP 5 DRILL DOCTOR AND/OR AIR TOOL REPAIRMAN; SCALER (DRILLER); FORM SETTER AND/OR BUILDER; WELDER AND/OR PIPELAYER INSTALLING PROCESS PIPING; DRILLER-CORE, DIAMOND, WAGON, AIR TRACK, JOY, MUSTANG, PR-143, 220 GARDNER-DENVER, HYDRASONIC, POWDERMAN; WATER BLASTER OPERATOR NOTE: $0.50 PER HOUR PREMIUM FOR PER … (the classification continues in the wage determination) | $31.98 | $9.26 | $41.24 | Union agreement LABO1184-006, 2025-06-01 · Price a crew using this row |
| LABORERS: GROUP 4 ASPHALT RAKER AND IRONER; AIR AND WATER WASHOUT NOZZLEMAN (LOW AND HIGH PRESSURE); SCALER (USING BOS'N'S CHAIR OR SAFETY BELT); TAMPER (MECHANICAL-ALL TYPES); SANDBLASTER (NOZZLEMAN); CONCRETE SAW (HAND-GUIDED); CONCRETE CUTTING TORCH; GUNITE (GUNMAN, MIXERMAN, RODMAN); BIO-FILER, PRESSMAN, INSTALLER, … (the classification continues in the wage determination) | $30.88 | $9.26 | $40.14 | Union agreement LABO1184-006, 2025-06-01 · Price a crew using this row | |
| LABORERS: GROUP 3 OPERATOR AND TENDER OF PNEUMATIC AND ELECTRIC TOOLS; CONCRETE VIBRATING MACHINES, CHAIN SAW (ON CLEARING AND GRUBBING); HYDRAULIC JACKS AND SIMILAR MECHANICAL TOOLS NOT SEPARATELY HEREIN CLASSIFIED; PIPE CAULKER AND/OR BACKUP MAN-PIPELINE; RIGGERS AND SIGNAL MAN-PIPELINE; PIPE WRAPPER; CRIBBER & SHORE … (the classification continues in the wage determination) | $29.91 | $9.26 | $39.17 | Union agreement LABO1184-006, 2025-06-01 · Price a crew using this row | |
| LABORERS: GROUP 2 CONCRETE LABORER (BELT, PIPE AND/OR HOSEMAN); CEMENT MASON TENDER; CUTTING TORCH OPERATOR; POWER TYPE CONCRETE BUGGY; BANDER; GUINEA CHASER | $29.05 | $9.26 | $38.31 | Union agreement LABO1184-006, 2025-06-01 · Price a crew using this row | |
| LABORERS: GROUP 1 LABORER, GENERAL OR CONSTRUCTION; TOOL DISPATCHER OR CHECKER; MANUALLY CONTROLLED SIGNAL OPERATOR; FENCE BUILDER, GUARD RAIL BUILDER-HIGHWAY; CHAT BOX MAN; DUMPMAN AND/OR SPOTTER; RIP RAP STONE MAN; ROCK SLINGER; FORM STRIPPER; PACKING ROD STEEL AND PANS; CESSPOOL DIGGERS AND INSTALLERS; ASTRO TURF LA … (the classification continues in the wage determination) | $27.41 | $9.26 | $36.67 | Union agreement LABO1184-006, 2025-06-01 · Price a crew using this row | |
| Ironworker | IRONWORKER ZONE 1: 0 TO 50 MILES FROM CITY HALL IN PHOENIX OR TUCSON ZONE 2: 050 TO 100 MILES - ADD $4.00 ZONE 3: 100 TO 150 MILES - ADD $5.00 ZONE 4: 150 MILES & OVER - ADD $6.50 | $33.00 | $19.91 | $52.91 | Union agreement IRON0075-001, 2025-08-01 · Price a crew using this row |
| Power equipment operator | POWER EQUIPMENT OPERATOR: GROUP 4 CRANE OPERATOR (PNEUMATIC OR CRAWLER-100 TONS HOISTING CAPACITY AND OVER, MRC RATING), SKIP LOADER (ALL TYPES WITH RATED CAPACITY OF 10 CU. YD. OR MORE), UNIVERSAL EQUIPMENT OPERATOR (BACKHOE, CLAMSHELL, DRAGLINE, SHOVEL, ETC., 10 CU. YD. AND OVER) MULTIPLE-UNIT EARTH EQUIPMENT (HOLLAN … (the classification continues in the wage determination) | $32.42 | $11.72 | $44.14 | Union agreement ENGI0428-002, 2020-06-01 · Price a crew using this row |
| POWER EQUIPMENT OPERATOR: GROUP 3 ASPHALT OR CONCRETE PLANING, ROTOMILL AND MILLING MACHINE, AUTO GRADE MACHINE (CMI AND SIMILAR EQUIPMENT), BORING MACHINE (INCLUDING MOLE, BADGER AND SIMILAR TYPE), CONCRETE PUMP (TRUCK MOUNTED WITH BOOM), CRANE (CRAWLER AND PNEUMATIC OVER 15 TONS BUT LESS THAN 100 TONS CAPACITY MRC), … (the classification continues in the wage determination) | $31.39 | $11.72 | $43.11 | Union agreement ENGI0428-002, 2020-06-01 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: GROUP 2 AGGREGATE PLANT (INCLUDING CRUSHING, SCREENING AND SAND PLANTS, ETC.), ASPHALT PLANT MIXER, ASPHALT LAYDOWN MACHINE, BACKHOE (RUBBER TIRED OR TRACK, LESS THAN 1 CU. YD. MRC), BEE GEE OPERATOR BORING MACHINE, CONCRETE BATCH PLANT (ALL TYPES AND SIZES), CONCRETE MECHANICAL TAMPING, SPREA … (the classification continues in the wage determination) | $30.31 | $11.72 | $42.03 | Union agreement ENGI0428-002, 2020-06-01 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: GROUP 1 A-FRAME BOOM TRUCK, WINCH TRUCK, AIR COMPRESSOR, BELTCRETE, BORING BRIDGE AND TEXTURE, CONCRETE MIXER (SKIP TYPE), CONDUCTOR, BRAKEMAN, HANDLER, CONVEYOR, CROSS TIMING AND PIPE FLOAT, CURING MACHINE, DINKY (UNDER 20 TONS), ELEVATOR HOIST (HUSKY AND SIMILAR), FIREMEN (ALL), FORKLIFT AND … (the classification continues in the wage determination) | $27.04 | $11.72 | $38.76 | Union agreement ENGI0428-002, 2020-06-01 · Price a crew using this row | |
| Cement mason / concrete finisher | CEMENT MASON/CONCRETE FINISHER | $28.78 | $9.17 | $37.95 | Union agreement PLAS0394-004, 2024-01-01 · Price a crew using this row |
| Bricklayer / tile / terrazzo | BRICKLAYER (MARICOPA, MOHAVE, PINAL, AND YUMA COUNTIES) ZONE PAY: (RADIUS MILES FROM THE INTERSECTION OF CENTRAL AVE. AND WASHINGTON ST., PHOENIX, AZ) ZONE A: 0-60 MILES- BASE RATE ZONE B: 61-75 MILES- BASE RATE PLUS $2.00 PER HOUR ZONE C: 75-100 MILES- BASE RATE PLUS $3.00 PER HOUR ZONE D: 101-200 MILES- BASE RATE PLU … (the classification continues in the wage determination) | $25.95 | $8.49 | $34.44 | Union agreement BRAZ0003-006, 2020-07-01 · Price a crew using this row |
| BRICKLAYER (PIMA COUNTY) ZONE PAY: (RADIUS MILES FROM THE INTERSECTION OF CENTRAL AVE. AND WASHINGTON ST., PHOENIX, AZ) ZONE A: 0-60 MILES- BASE RATE ZONE B: 61-75 MILES- BASE RATE PLUS $2.00 PER HOUR ZONE C: 75-100 MILES- BASE RATE PLUS $3.00 PER HOUR ZONE D: 101-200 MILES- BASE RATE PLUS $3.50 PER HOUR ZONE E: OVER 2 … (the classification continues in the wage determination) | $25.31 | $8.13 | $33.44 | Union agreement BRAZ0003-012, 2019-07-01 · Price a crew using this row | |
| Painter | PAINTER | $25.47 | $8.00 | $33.47 | Union agreement PAIN0086-004, 2024-04-01 · Price a crew using this row |
| Truck driver | TRUCK DRIVER GROUP 6- 7-AXLE DUMP, 8-AXLE DUMP FOOTNOTE: HEALTH & WELFARE $1,330.26 PER MONTH IN ADDITIONAL FRINGE BENEFITS. AS OF SEPTEMBER 1, 2024 | $29.47 | $1.65 | $31.12 | Union agreement TEAM0104-002, 2024-07-01 · Price a crew using this row |
| TRUCK DRIVER GROUP 5- 6-AXLE DUMP FOOTNOTE: HEALTH & WELFARE $1,330.26 PER MONTH IN ADDITIONAL FRINGE BENEFITS. AS OF SEPTEMBER 1, 2024 | $27.80 | $1.65 | $29.45 | Union agreement TEAM0104-002, 2024-07-01 · Price a crew using this row | |
| TRUCK DRIVER GROUP 4- 5 AXLE DUMP, WATER TRUCK 4000 GAL AND OVER FOOTNOTE: HEALTH & WELFARE $1,330.26 PER MONTH IN ADDITIONAL FRINGE BENEFITS. AS OF SEPTEMBER 1, 2024 | $28.68 | $1.65 | $30.33 | Union agreement TEAM0104-002, 2024-07-01 · Price a crew using this row | |
| TRUCK DRIVER GROUP 3- 4 AXLE DUMP, WATER TRUCK DRIVE- (2500 GAL BUT LESS THAN 4000 GAL) FOOTNOTE: HEALTH & WELFARE $1,330.26 PER MONTH IN ADDITIONAL FRINGE BENEFITS. AS OF SEPTEMBER 1, 2024 | $27.43 | $1.65 | $29.08 | Union agreement TEAM0104-002, 2024-07-01 · Price a crew using this row | |
| TRUCK DRIVER GROUP 2: 2 OR 3 AXLE DUMP , WATER TRUCK UNDER 2500 GAL. FOOTNOTE: HEALTH & WELFARE $1,330.26 PER MONTH IN ADDITIONAL FRINGE BENEFITS. AS OF SEPTEMBER 1, 2024 | $26.95 | $1.65 | $28.60 | Union agreement TEAM0104-002, 2024-07-01 · Price a crew using this row |
Building
AZ20260043, modification 1 (published 2026-05-18)
Common trades from this wage determination. It lists 18 classifications in total; the full text is on SAM.gov.
| Trade | Classification | Base | Fringe | Listed total | Where the rate comes from |
|---|---|---|---|---|---|
| Electrician | ELECTRICIAN | $39.09 | $15.53 | $54.62 | Union agreement ELEC0640-002, 2025-07-01 · Price a crew using this row |
| Plumber / pipefitter | PLUMBER | $51.15 | $21.00 | $72.15 | Union agreement PLUM0469-010, 2025-07-01 · Price a crew using this row |
| PIPEFITTER | $51.15 | $21.00 | $72.15 | Union agreement PLUM0469-010, 2025-07-01 · Price a crew using this row | |
| Carpenter | CARPENTER | $33.19 | $19.20 | $52.39 | Union agreement CARP1912-001, 2025-07-01 · Price a crew using this row |
| Laborer | LABORER: PIPELAYER | $16.77 | $1.05 | $17.82 | DOL survey SUAZ2019-006, 2023-06-12 · Price a crew using this row |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $18.90 | $0.00 | $18.90 | DOL survey SUAZ2019-006, 2023-06-12 · Price a crew using this row | |
| LABORER: COMMON OR GENERAL | $16.00 | $0.00 | $16.00 | DOL survey SUAZ2019-006, 2023-06-12 · Price a crew using this row | |
| Ironworker | IRONWORKER | $33.00 | $19.91 | $52.91 | Union agreement IRON0075-012, 2025-08-01 · Price a crew using this row |
| Power equipment operator | POWER EQUIPMENT OPERATOR: LOADER | $34.96 | $13.52 | $48.48 | Union agreement ENGI0428-017, 2023-06-01 · Price a crew using this row |
| POWER EQUIPMENT OPERATOR: CRANE | $36.04 | $13.52 | $49.56 | Union agreement ENGI0428-017, 2023-06-01 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: BULLDOZER | $31.69 | $13.52 | $45.21 | Union agreement ENGI0428-017, 2023-06-01 · Price a crew using this row | |
| OPERATOR: ROLLER | $23.62 | $6.44 | $30.06 | DOL survey SUAZ2019-006, 2023-06-12 · Price a crew using this row | |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $24.97 | $5.41 | $30.38 | DOL survey SUAZ2019-006, 2023-06-12 · Price a crew using this row | |
| Cement mason / concrete finisher | CEMENT MASON/CONCRETE FINISHER | $22.00 | $0.00 | $22.00 | DOL survey SUAZ2019-006, 2023-06-12 · Price a crew using this row |
| Bricklayer / tile / terrazzo | BRICKLAYER | $32.29 | $9.97 | $42.26 | Union agreement BRAZ0003-001, 2024-07-01 · Price a crew using this row |
| TILE SETTER | $21.50 | $0.00 | $21.50 | DOL survey SUAZ2019-006, 2023-06-12 · Price a crew using this row | |
| Painter | PAINTER | $16.48 | $0.00 | $16.48 | DOL survey SUAZ2019-006, 2023-06-12 · Price a crew using this row |
| Sheet metal worker | SHEET METAL WORKER | $49.39 | $19.86 | $69.25 | Union agreement SHEE0359-001, 2025-07-01 · Price a crew using this row |
Highway
AZ20260046, modification 1 (published 2026-05-18)
Common trades from this wage determination. It lists 46 classifications in total; the full text is on SAM.gov.
| Trade | Classification | Base | Fringe | Listed total | Where the rate comes from |
|---|---|---|---|---|---|
| Electrician | ELECTRICIAN | $29.00 | $7.58 | $36.58 | DOL survey SUAZ2023-023, 2024-11-19 · Price a crew using this row |
| Carpenter | CARPENTER, EXCLUDES FORMWORK CONCRETE | $35.89 | $14.98 | $50.87 | Union agreement CARP1912-003, 2024-07-01 · Price a crew using this row |
| CARPENTER: FORMWORK CONCRETE | $31.98 | $9.26 | $41.24 | Union agreement LABO1184-037, 2024-06-01 · Price a crew using this row | |
| Laborer | LABORER: FENCE ERECTOR | $27.41 | $9.26 | $36.67 | Union agreement LABO1184-017, 2025-06-01 · Price a crew using this row |
| LABORER: ASPHALT, INCLUDES RAKER, SHOVELER, SPREADER AND DISTRIBUTOR | $29.91 | $9.26 | $39.17 | Union agreement LABO1184-025, 2025-06-01 · Price a crew using this row | |
| LABORER: GRADE SETTER | $29.91 | $9.26 | $39.17 | Union agreement LABO1184-027, 2025-06-01 · Price a crew using this row | |
| LABORER: MASON TENDER | $29.91 | $9.26 | $39.17 | Union agreement LABO1184-030, 2025-06-01 · Price a crew using this row | |
| LABORER: PIPELAYER | $30.88 | $9.26 | $40.14 | Union agreement LABO1184-032, 2025-06-01 · Price a crew using this row | |
| LABORER: LANDSCAPE LABORER | $18.03 | $0.00 | $18.03 | DOL survey SUAZ2023-023, 2024-11-19 · Price a crew using this row | |
| LABORER: GENERAL | $22.35 | $0.60 | $22.95 | DOL survey SUAZ2023-023, 2024-11-19 · Price a crew using this row | |
| LABORER: CONCRETE SAW (HAND HELD/WALK BEHIND) | $25.22 | $5.08 | $30.30 | DOL survey SUAZ2023-023, 2024-11-19 · Price a crew using this row | |
| Ironworker | IRONWORKER | $33.15 | $18.57 | $51.72 | DOL survey SUAZ2023-023, 2024-11-19 · Price a crew using this row |
| Power equipment operator | POWER EQUIPMENT OPERATOR: BULLDOZER | $35.56 | $18.12 | $53.68 | Union agreement ENGI0012-046, 2024-12-01 · Price a crew using this row |
| POWER EQUIPMENT OPERATOR: PAVER/SPREADER/FINISH EQUIPMENT (ASPHALT, AGGREGATE, & CONCRETE) | $35.56 | $18.12 | $53.68 | Union agreement ENGI0012-051, 2024-12-01 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: SCRAPER | $35.56 | $18.12 | $53.68 | Union agreement ENGI0012-052, 2024-12-01 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: TRACTOR | $35.56 | $18.12 | $53.68 | Union agreement ENGI0012-053, 2024-12-01 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: (DRILL RIG/AUGER) | $36.64 | $18.12 | $54.76 | Union agreement ENGI0012-057, 2024-12-01 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $32.29 | $18.12 | $50.41 | Union agreement ENGI0012-064, 2024-12-01 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: BACKHOE/BACKHOE & LOADER COMBO/TRACK BACKHOE | $35.56 | $18.12 | $53.68 | Union agreement ENGI0012-066, 2024-12-01 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: CRANE/DERRICK | $36.64 | $18.12 | $54.76 | Union agreement ENGI0012-071, 2024-12-01 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: MOTOR GRADER/BLADE | $36.64 | $18.12 | $54.76 | Union agreement ENGI0012-074, 2024-12-01 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: MECHANIC | $37.67 | $18.12 | $55.79 | Union agreement ENGI0012-075, 2024-12-01 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: HORIZONTAL DIRECTIONAL DRILL | $31.98 | $9.26 | $41.24 | Union agreement LABO1184-016, 2025-06-01 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: TRENCHER | $30.88 | $9.26 | $40.14 | Union agreement LABO1184-033, 2025-06-01 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: FORKLIFT | $30.88 | $9.26 | $40.14 | Union agreement LABO1184-044, 2025-06-01 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: OILER | $31.56 | $10.69 | $42.25 | DOL survey SUAZ2023-023, 2024-11-19 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: MILLING MACHINE | $30.09 | $6.45 | $36.54 | DOL survey SUAZ2023-023, 2024-11-19 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: LOADER/FRONT END LOADER | $30.15 | $0.81 | $30.96 | DOL survey SUAZ2023-023, 2024-11-19 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: GRADE CHECKER | $29.74 | $13.07 | $42.81 | DOL survey SUAZ2023-023, 2024-11-19 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: FIELD EQUIPMENT SERVICEPERSON | $35.39 | $11.50 | $46.89 | DOL survey SUAZ2023-023, 2024-11-19 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: EXCAVATOR/TRACKHOE | $31.27 | $6.90 | $38.17 | DOL survey SUAZ2023-023, 2024-11-19 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: CONCRETE SCREED | $25.70 | $7.15 | $32.85 | DOL survey SUAZ2023-023, 2024-11-19 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: CONCRETE PUMP TRUCK | $43.11 | $10.87 | $53.98 | DOL survey SUAZ2023-023, 2024-11-19 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: COMPACTOR/ROLLER | $28.29 | $6.46 | $34.75 | DOL survey SUAZ2023-023, 2024-11-19 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: BROOM/SWEEPER | $26.47 | $7.26 | $33.73 | DOL survey SUAZ2023-023, 2024-11-19 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: BOOM/CRANE TRUCK | $43.11 | $10.87 | $53.98 | DOL survey SUAZ2023-023, 2024-11-19 · Price a crew using this row | |
| Cement mason / concrete finisher | CEMENT MASON/CONCRETE FINISHER | $30.09 | $0.00 | $30.09 | DOL survey SUAZ2023-023, 2024-11-19 · Price a crew using this row |
| Painter | PAINTER: SIGN AND DISPLAY ERECTOR | $18.03 | $0.00 | $18.03 | DOL survey SUAZ2023-023, 2024-11-19 · Price a crew using this row |
| PAINTER: PAVEMENT MARKING | $24.60 | $6.34 | $30.94 | DOL survey SUAZ2023-023, 2024-11-19 · Price a crew using this row | |
| Truck driver | TRUCK DRIVER: OFF ROAD TRUCK | $35.56 | $18.12 | $53.68 | Union agreement ENGI0012-070, 2024-12-01 · Price a crew using this row |
| TRUCK DRIVER: CONCRETE | $30.88 | $9.26 | $40.14 | Union agreement LABO1184-047, 2025-06-01 · Price a crew using this row | |
| TRUCK DRIVER: WATER | $30.88 | $9.26 | $40.14 | Union agreement LABO1184-049, 2025-06-01 · Price a crew using this row | |
| TRUCK DRIVER: SWEEPER | $20.24 | $5.48 | $25.72 | DOL survey SUAZ2023-023, 2024-11-19 · Price a crew using this row | |
| TRUCK DRIVER: OIL DISTRIBUTOR | $29.75 | $8.04 | $37.79 | DOL survey SUAZ2023-023, 2024-11-19 · Price a crew using this row | |
| TRUCK DRIVER: DUMP | $25.78 | $0.69 | $26.47 | DOL survey SUAZ2023-023, 2024-11-19 · Price a crew using this row |
Heavy
AZ20260058, modification 1 (published 2026-05-18)
Common trades from this wage determination. It lists 33 classifications in total; the full text is on SAM.gov.
| Trade | Classification | Base | Fringe | Listed total | Where the rate comes from |
|---|---|---|---|---|---|
| Electrician | ELECTRICIAN | $33.00 | $13.04 | $46.04 | Union agreement ELEC0570-014, 2025-06-01 · Price a crew using this row |
| ELECTRICIAN: LINEPERSON | $62.08 | $22.49 | $84.57 | Union agreement ELEC0769-001, 2025-08-04 · Price a crew using this row | |
| ELECTRICIAN: GROUNDPERSON | $36.00 | $16.88 | $52.88 | Union agreement ELEC0769-003, 2025-08-04 · Price a crew using this row | |
| ELECTRICIAN: LINE EQUIPMENT OPERATOR | $46.56 | $19.15 | $65.71 | Union agreement ELEC0769-004, 2025-08-04 · Price a crew using this row | |
| Carpenter | CARPENTER: FORMWORK CONCRETE | $31.98 | $9.26 | $41.24 | Union agreement LABO1184-050, 2025-06-01 · Price a crew using this row |
| Laborer | LABORER: GENERAL | $27.41 | $9.26 | $36.67 | Union agreement LABO1184-012, 2025-06-01 · Price a crew using this row |
| LABORER: JACKHAMMER | $29.05 | $9.26 | $38.31 | Union agreement LABO1184-013, 2025-06-01 · Price a crew using this row | |
| LABORER: PIPELAYER | $29.91 | $9.26 | $39.17 | Union agreement LABO1184-014, 2025-06-01 · Price a crew using this row | |
| LABORER: ASPHALT, INCLUDES RAKER, SHOVELER, SPREADER AND DISTRIBUTOR | $29.05 | $9.26 | $38.31 | Union agreement LABO1184-022, 2025-06-01 · Price a crew using this row | |
| LABORER: GRADE SETTER | $29.91 | $9.26 | $39.17 | Union agreement LABO1184-028, 2025-06-01 · Price a crew using this row | |
| LABORER: MASON TENDER | $27.79 | $8.87 | $36.66 | DOL survey SUUAVGAZ0005, 2025-01-01 · Price a crew using this row | |
| Power equipment operator | POWER EQUIPMENT OPERATOR: OILER | $32.29 | $18.12 | $50.41 | Union agreement ENGI0012-035, 2024-12-01 · Price a crew using this row |
| POWER EQUIPMENT OPERATOR: FIELD EQUIPMENT SERVICEPERSON | $35.56 | $18.12 | $53.68 | Union agreement ENGI0012-037, 2024-12-01 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: CRANE/DERRICK | $36.64 | $18.12 | $54.76 | Union agreement ENGI0012-042, 2024-12-01 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: MECHANIC | $37.67 | $18.12 | $55.79 | Union agreement ENGI0012-043, 2024-12-01 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $32.29 | $18.12 | $50.41 | Union agreement ENGI0012-044, 2024-12-01 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: BACKHOE/BACKHOE & LOADER COMBO/TRACK BACKHOE | $35.56 | $18.12 | $53.68 | Union agreement ENGI0012-045, 2024-12-01 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: BULLDOZER | $35.56 | $18.12 | $53.68 | Union agreement ENGI0012-046, 2024-12-01 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: COMPACTOR/ROLLER | $35.56 | $18.12 | $53.68 | Union agreement ENGI0012-047, 2024-12-01 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: (DRILL RIG/AUGER) | $35.56 | $18.12 | $53.68 | Union agreement ENGI0012-048, 2024-12-01 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: LOADER/FRONT END LOADER | $35.56 | $18.12 | $53.68 | Union agreement ENGI0012-049, 2024-12-01 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: TRENCHER | $35.56 | $18.12 | $53.68 | Union agreement ENGI0012-054, 2024-12-01 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: EXCAVATOR/TRACKHOE | $36.64 | $18.12 | $54.76 | Union agreement ENGI0012-058, 2024-12-01 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: GRADE CHECKER | $36.64 | $18.12 | $54.76 | Union agreement ENGI0012-059, 2024-12-01 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: MOTOR GRADER/BLADE | $36.64 | $18.12 | $54.76 | Union agreement ENGI0012-061, 2024-12-01 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: FORKLIFT | $30.88 | $9.26 | $40.14 | Union agreement LABO1184-015, 2025-06-01 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: HORIZONTAL DIRECTIONAL DRILL | $31.98 | $9.26 | $41.24 | Union agreement LABO1184-016, 2025-06-01 · Price a crew using this row | |
| POWER EQUIPMENT OPERATOR: SCRAPER | $32.41 | $0.00 | $32.41 | DOL survey SUAZ2023-008, 2024-11-19 · Price a crew using this row | |
| Truck driver | TRUCK DRIVER: HYDROVAC | $35.56 | $18.12 | $53.68 | Union agreement ENGI0012-055, 2024-12-01 · Price a crew using this row |
| TRUCK DRIVER: CONCRETE | $30.88 | $9.26 | $40.14 | Union agreement LABO1184-034, 2025-06-01 · Price a crew using this row | |
| TRUCK DRIVER: DUMP | $30.88 | $9.26 | $40.14 | Union agreement LABO1184-035, 2025-06-01 · Price a crew using this row | |
| TRUCK DRIVER: WATER | $30.88 | $9.26 | $40.14 | Union agreement LABO1184-036, 2025-06-01 · Price a crew using this row |
Next steps
From the rate to the payroll
- Price a crew from these rates — total package, cash in lieu of fringe and overtime on the base rate.
- Report them on Form WH-347 — the weekly federal certified payroll, column by column (Rev. January 2025).
- What Arizona requires for certified payroll — the state report, its cadence and its source, next to the federal rule.
Other Arizona counties
Apache · Cochise · Coconino · Gila · Graham · Greenlee · La Paz · Maricopa · Navajo · Pima · Pinal · Santa Cruz · Yavapai · Yuma