Does CHIPS Act funding trigger Davis-Bacon prevailing wage?

Yes. Construction of a facility funded under the CHIPS incentives program is subject to Davis-Bacon prevailing wage requirements.

Check coverage indicators Model LA County crew cost

Short answer

Yes. Construction of a facility funded under the CHIPS incentives program is subject to Davis-Bacon prevailing wage requirements.

How the requirement attaches

The CHIPS statute and the Department of Commerce program terms require that laborers and mechanics employed by contractors and subcontractors on CHIPS-funded facility construction be paid at least the Davis-Bacon prevailing wages for the locality.

Bid-file implication

Treat CHIPS-funded semiconductor facility work like federal construction: use the incorporated wage determination and submit certified payroll.

Guardrail

Screening only—not a coverage determination, tax opinion, or legal advice. Confirm the program-specific rules, exceptions, contract clauses, incorporated wage determination, and any separate federal, state, or local requirements before bidding, paying workers, filing payroll reports, or claiming a tax benefit.

FAQ

Frequently asked questions

Does CHIPS Act funding require Davis-Bacon prevailing wages?

Yes. Construction of a facility funded under the CHIPS incentives program is subject to Davis-Bacon prevailing wage requirements.

What happens when both federal and state prevailing wage apply?

Both regimes may impose requirements, but the answer is jurisdiction- and contract-specific. Compare the incorporated federal determination with the applicable state schedule, then verify classifications, fringes, overtime, apprentices, dates, exemptions, and contract clauses with the awarding agency or qualified adviser.

Do I still need certified payroll?

Covered DBRA contractors and subcontractors generally must submit weekly certified payroll showing the classifications and rates paid. Confirm the reporting clause in the specific contract.

Official sources

Check the contract file before bid close